CITY OF FERNDALE RESOURCES:

Sidewalk Inspections and Replacement Program

The City of Ferndale uses a recurring biennial Sidewalk Replacement Program to maintain safe pedestrian access throughout the community. On even numbered years, the DPW identifies sidewalk flags that are broken, deteriorated, uneven, or otherwise non-compliant and coordinates replacement through a district-based construction process.

 

This program is intended to improve safety, maintain walkability, and complete sidewalk work efficiently across larger areas of the City.

Why the Program Exists

Sidewalks are public infrastructure, but under City ordinance and policy, the adjacent property owner is generally responsible for maintaining the sidewalk next to their property.

 

The City uses a district-based program because replacing sidewalks on a property-by-property basis is less efficient and more expensive for residents. Grouping work by district allows the City to inspect larger areas, bid the work competitively, coordinate construction, and achieve economies of scale.

 

The program also helps ensure that sidewalk conditions are evaluated consistently across the district.

District Rotation

Ferndale is divided into ten sidewalk districts. Each cycle, selected districts are inspected to determine which sidewalk flags require replacement.

 

This allows the City to review the sidewalk network over time while keeping the program manageable for residents, DPW, contractors, and City Council.

 

The district map is updated as the program advances.

Inspection Process

DPW inspects sidewalks within the selected district. Sidewalk flags are reviewed for defects and non-compliant conditions. Sidewalk panels identified for replacement are typically marked in the field.

 

The City uses inspection criteria to determine whether sidewalk replacement is required. Common reasons for replacement include:

 

  • Stubbers or vertical separation: Two adjacent sidewalk flags with a vertical separation greater than one-half inch.
  • Cracks: A broken sidewalk flag with a single crack or multiple cracks.
  • Drainage issue: A sidewalk flag that has sunken and collects water over more than 25% of the flag. This also includes driveway sidewalk flags that have sunk below the height of the driveway approach.
  • Holes or pitting: Missing concrete greater than two inches in any direction, severe pitting over more than 25% of the flag, or deteriorated control joints creating a crevasse greater than two inches wide.
  • Scaling: Flaking or peeling away of more than 25% of the surface mortar, resulting in a gravel-like surface.
  • Excessive slope: A sidewalk flag with a side slope greater than 3 inches per 5 feet, or more than 1 inch per foot along the travel path.
  • Other hazardous or deteriorated conditions: A non-typical condition where the inspector identifies a hazard or deterioration, such as mortar creating a trip hazard, asphalt patching, or another unsafe condition.

Public Hearing and Notification Process

In early spring, property owners are notified if sidewalk replacement is required adjacent to their property.

 

The notice typically includes:

  • A description of the required replacement
  • Estimated quantities
  • Estimated cost
  • Information about the public hearing
  • Instructions for contesting or asking questions about the proposed replacement
  • Information about hardship consideration, when applicable

A public hearing is held before City Council to establish the Special Assessment District and hear resident comments or objections, typically in May.

 

Residents who cannot attend the public hearing may submit written comments to the City Clerk by the deadline provided in the notice.

Horizontal Sawcutting

In some cases, smaller eligible trip hazards may be corrected through horizontal sawcutting instead of full replacement.

 

Sawcutting may be used where the vertical separation is small and there are no other defects requiring replacement. If a sidewalk flag is cracked, deteriorated, sunken, pitted, or otherwise damaged beyond repair, replacement is required.

Contractor Selection and Construction

The City competitively bids the sidewalk replacement work through a formal bid process. A contractor is selected based on the bid results and City review.

 

The contractor performs the sidewalk replacement work using unit prices established through the bid. Final payment is based on actual field measurements.

 

During construction:

  • Existing sidewalk sections are removed
  • Replacement concrete is poured
  • Temporary access disruptions may occur
  • Residents should avoid newly poured concrete until it has cured

The City works to complete the project efficiently and minimize disruption within the district. 

Cost and Special Assessment District

Sidewalk replacement is funded through a Special Assessment District.

 

Property owners are responsible for the cost of sidewalk replacement adjacent to their property. Costs are based on actual measurements and the unit prices from the awarded contract.

 

Typical sidewalk thickness varies by use:

  • 4-inch sidewalk is typically used for standard residential sidewalk
  • 6-inch sidewalk is typically used through residential driveway areas
  • 8-inch sidewalk may be required for commercial driveway areas or heavier vehicle use

City Responsibility

The City pays for certain sidewalk work that serves a broader community purpose, including:

  • ADA ramps at corner properties
  • Detectable warning surfaces
  • Sidewalks adjacent to City-owned property

ADA ramps and curb-related accessibility improvements provide a community-wide public access benefit and are not simply individual property frontage maintenance.

Trees and Sidewalks

Tree roots may contribute to sidewalk movement or lifting. The City does not require tree removal as part of the sidewalk replacement program.

 

Where sidewalk work is needed near trees, the City works to complete the sidewalk repair while preserving the tree canopy whenever possible.

Payment and Billing

After construction is complete, final quantities are calculated and final assessment amounts are mailed to affected property owners.

 

The assessment is typically billed as a lump sum. If the assessment is not paid, the unpaid amount may be placed on the property tax roll in accordance with City procedures.

 

Property owners selling a property before final billing should disclose the pending assessment to the buyer.

 

 

Hardship Consideration: 

The City provides a hardship process for qualifying residents. Property owners may qualify for additional time to pay if:

  • The special assessment is $500 or more, and household income is $20,000 or less; or
  • The property is a residential corner lot and the side-frontage sidewalk cost is $500 or more.

Council adjusts these thresholds during the active sidewalk program.

 

Residents who do not meet these thresholds but believe the assessment creates a hardship may still request consideration. The hardship process typically occurs after final cost letters are mailed, following the construction, in the fall.

Appeals and Questions

Residents may contact DPW to ask questions about inspection results, replacement requirements, or program timing.

 

Residents may also attend the public hearing or submit written comments if they wish to contest the replacement requirement or discuss concerns before Council action.